MUTCD Rules Data

TrafficCAD does not link to the manual — it encodes it. Every distance a generated plan prints comes from the tables below, and every one of them carries its citation into the UI, the plan, and the exported PDF.

This page is the reference for what is encoded, so you can check a computed number against the source without opening the app.

Edition tracked: MUTCD 11th Edition, Revision 1 (December 2025).

State supplements override these

With a state standard selected, its supplement takes precedence where it differs from the national manual. Texas TMUTCD 2025 and California MUTCD 2026 ship as complete libraries — see State Standards & Libraries.

Taper length

Taper length L is computed from the posted or anticipated operating speed S and the lateral offset W, per Table 6B-4:

Speed Formula
40 mph or less L = WS² / 60
45 mph or more L = WS

Table 6B-3 then sets the required length for each taper type as a multiple of L:

Taper type Required length Citation
Merging at least L Table 6B-3
Shifting at least 0.5 L Table 6B-3
Shoulder at least 0.33 L Table 6B-3
One-lane, two-way 50–100 ft Table 6B-3
Downstream 50–100 ft Table 6B-3

See Taper a Work Zone by Hand for the calculator that applies this.

Buffer space

Longitudinal buffer space equals stopping sight distance for the speed, per Table 6B-2. Buffer space is an Option in the manual; when it is used, these lengths apply.

Speed (mph) Buffer (ft) Speed (mph) Buffer (ft)
20 115 50 425
25 155 55 495
30 200 60 570
35 250 65 645
40 305 70 730
45 360 75 820

Advance warning sign spacing

Distances A, B, and C between advance warning signs, per Table 6B-1, selected from the road context:

Road context A B C
Urban, low speed 100 ft 100 ft 100 ft
Urban, high speed 350 ft 350 ft 350 ft
Rural 500 ft 500 ft 500 ft
Expressway / freeway 1,000 ft 1,500 ft 2,640 ft

Channelizing device spacing

Maximum spacing between channelizing devices, per §6K.01 ¶04–05:

  • In a taper: 1 × speed in mph, as feet (45 ft at 45 mph).
  • On a tangent: 2 × speed in mph, as feet (90 ft at 45 mph).
  • In a 50–100 ft taper (one-lane two-way, downstream): approximately 20 ft, per §6B.08 ¶12/¶14.

Spacing a run at the taper maximum keeps the whole run compliant, since the tangent allowance is looser. See Channelizing Devices.

Other encoded rules

Rule Value Citation
TTC speed reduction limit 10 mph maximum §6B.01 ¶17–20
Minimum lane width 10 ft; 9 ft short-term, low-volume / low-speed §6N.07 ¶02–04
Sign mounting heights 5 ft rural, 7 ft urban/business, 1 ft minimum portable §6F.02
Portable low-mount signs 3 days maximum (Guidance) §6F.02 ¶11
Crashworthy supports Standard §6F.02 ¶15 / §6A.04
Flagger stations Visible at the Table 6B-2 distance for the speed §6D.06
Arrow board requirements By closure type and speed §6L.06
Type 3 barricades and sign coverage Encoded per the barricade rules §6K

Typical applications

The MUTCD Chapter 6P typical applications (TA-1 … TA-54) ship as editable templates, and the closure classifier maps a drawn work zone to the applicable TA. See Typical Applications & Templates.

Reading a citation on a plan

Generated plans print the citation next to the value, in the form MUTCD 11th Ed. Table 6B-4 or MUTCD 11th Ed. §6K.01 ¶04–05. If a number looks wrong, the citation tells you exactly which table to check — and the inputs that drove it (speed, offset, road context) are on the road and the run that produced it.

Computed is not approved

Encoding the manual removes arithmetic errors, not engineering judgement. Every plan remains a draft requiring review and approval by a qualified engineer, per MUTCD §6P.01.